Acc561 Managerial Accounting: E9-7 Neely, Inc., is preparing its direct labor budget

Important Reminder!!! There might be other versions of this problem - amounts and dates have been changed - so please make sure you review and compare this tutorial to the problem in your homework. Even with different amounts, format and way of solving the problem is still the same so pleases be guided accordingly.

Acc561 Managerial Accounting
E9-7
Neely, Inc., is preparing its direct labor budget for 2008 from the following production budget based on a calendar year.
Quarter Units Quarter Units
1 20,000 3 35,000
2 25,000 4 30,000
Each unit requires 1.6 hours of direct labor.

Prepare a direct labor budget for 2008. Wage rates are expected to be $15 for the first 2 quarters and $16 for quarters 3 and 4.