Intermediate Accounting: E18-10 Berstler Construction Company began operations

Intermediate Accounting 
E18-10 Long-Term Contract Reporting 
Berstler Construction Company began operations in 2010. Construction activity for the first year is shown below. All contracts are with different customers, and any work remaining at December 31, 2010, is expected to be completed in 2011. 
Project Total Contract Price Billings through 12/31/10 Cash Collections through 12/31/10 Contract Costs Incurred through 12/31/10 Estimated Additional Costs to Complete 
1 560,000 360,000 340,000 450,000 130,000 
2 670,000 220,000 210,000 126,000 504,000 
3 520,000 500,000 440,000 330,000 - 
$1,750,000 $1,080,000 $990,000 $906,000 $634,000 

Prepare a partial income statement and balance sheet to indicate how the above information would be reported for financial statement purposes. Berstler Construction Company uses the completed-contract method. (For negative numbers use either a negative sign preceding the number, e.g. -45 or parenthesis, e.g. (45).)