Acc422 Intermediate Accounting: P10-6 Greig Landscaping began construction of a new plant

Acc422 Intermediate Accounting

P10-6 Interest during Construction
Greig Landscaping began construction of a new plant on December 1,2012. On this date, the company purchased a parcel of land for $139,000 in cash. In addition it paid $2,000 in survey cost and $4,000 for title insurance policy. An old dwelling on the premises was demolished at a cost of $3,000 with $1,000 being received from the sale of materials.
Architectural plans were also on December 1, 2012 when the architect was paid $30,000. The necessary building permits costing $3,000 were obtained from the city and paid for on December 1 as well. The excavation work began during the first week in December with payments made to the contractor as follows:
Date of payment Amount of payment
March 1 240,000
May 1 330,000
July 1 60,000
The building was completed on July 1, 2013. To finance consturction of this plant, Greig borrowed $600,000 from the bank on December 1, 2012. Greig had no other borrowings. The $600,000 was a 10-year loan bearing interest at 8%.

Instructions:
Compute the balance in each of the following accounts at December 31, 2012, and December 31, 2013. (Round amounts to the nearest dollar).
a. Land
b. Buildings
c. Interest Expense

Powered by